Project Dashboard

Week of May 18 โ€“ May 24, 2026
Infinum
This week
18.2h
Worked to date
157.2h
Engagement ceiling
607h
607.4h in Productive
Remaining
449.8h
25.9% consumed
Emerge Apps - Emerge Apps Website Rebuild Project
Emerge Apps
25.9%
18.2h this week 157.2h / 607.4h total 450.1h remaining
ServiceWorkedBudgeted%
Planning & AI Setup Non-billable 48h โ€” Non-billable
Discovery 97.9h 208h 47.1%
Visual Design 32.2h 50h 64.5%
PM & Meetings 24.6h 98h 25.1%
WordPress 2.5h 150h 1.7%
Quality Assurance 0h 24.4h 0.0%
UX 0h 77h 0.0%
TicketWorkedBudgeted%
Stakeholder Sessions 2h 3h 66.7%
[Future] Buyer Journey / CTA Mapping 3h 10h 30.0%
Directional Messaging Framework & Topic Strategy 1.2h 10h 12.5%
Voice & Tone Guidelines 1h 10h 10.0%
Preliminary IA [Flow Diagrams, Sitemap, Navigation Wires] 1h 10h 10.0%
TicketWorkedBudgeted%
๐Ÿšจ Context & Framing Workshop 14.2h 10h 142.5%
๐Ÿšจ [Current] Buyer Journey Mapping Workshop 22h 20h 110.0%
๐Ÿšจ Existing Research Review 10.5h 10h 105.0%
๐Ÿšจ Stakeholder Sessions 3h 3h 100.0%
๐Ÿ”ฅ Art Direction 17.5h 20h 87.5%
Design Phase Gate: May 26, 2026 8d to gate
Visual Design 50h allocation
~27.6h10.8h31.2h33.8h28.8h34.5h18.2hAprMay18 MayJunJulAugSep
~28.8h/wk ยท on pace with ~27.6h baseline
Ideal (28โ€“40h)Under (<28h)Over (>40h)Logged (past)
Sprint 0Sprint 1Sprint 2Sprint 3
6 Apr13 Apr20 Apr27 Apr4 May11 May18 May25 May
Shannon
Planning
2.2h
9.2h
15.5h
3h
9h
51.2h6.8h in
Marci
Planning
5h
11.5h
2.5h
17.5h
6.5h
27h5h in
55.5h
Todd
Planning
8h
9.5h
1.2h
15.5h
Reid
Planning
1h
1h
Ryan
Planning
1h
Dan
Planning
1h
1.2h
2.5h
0.4h
Tito
Planning
2.5h
2.5h
3.2h
3.5h
3.5h
3.5h6h in
3.5h
Risk Tracker
Short-term — within 2 weeks
Content dependency on EAManual
All new copy and CMS content entry is EA's responsibility. Delays in content delivery will directly impact timeline and could push launch.
CMS decision pendingManual
Final platform (WordPress vs. Webflow vs. Framer) is determined in Phase 1. A late or changed decision could compress the dev timeline.
Stakeholder availabilityManual
Key interviews with Dustin Boss and Alicia Torres need to happen early in discovery. Scheduling delays slow the entire strategy phase.
48-hour feedback SLAManual
SOW requires EA to provide feedback within 48 hours. Missed windows compound across phases.
Long-term — 2+ weeks
Burn rate trending toward ceilingData
At the current pace of 29h/week, the 607h engagement ceiling will be reached in ~16 weeks. Project runs 24 weeks total.
Buffer budget governanceManual
The $16,500 buffer is only invoiced on the final invoice. Need clear internal tracking so there are no surprises if scope creep triggers it.
AI workflow frictionManual
The AI-forward approach is intended to save time. If tools fail to produce usable drafts, effort may increase beyond estimates.