Project Dashboard

Week of May 11 – May 17, 2026
Infinum
This week
9.2h
Worked to date
113.8h
Engagement ceiling
607h
607.4h in Productive
Remaining
493.2h
18.8% consumed
Emerge Apps - Emerge Apps Website Rebuild Project
Emerge Apps
18.7%
9.2h this week 113.8h / 607.4h total 493.6h remaining
ServiceWorkedBudgeted%
Planning & AI Setup Non-billable 47.5h Non-billable
Discovery 80.2h 208h 38.5%
Visual Design 17.2h 50h 34.5%
PM & Meetings 13.9h 98h 14.2%
WordPress 2.5h 150h 1.7%
Quality Assurance 0h 24.4h 0.0%
UX 0h 77h 0.0%
TicketWorkedBudgeted%
[Future] Buyer Journey / CTA Mapping 3h 10h 30.0%
[Current] Buyer Journey Mapping Workshop 2.5h 10h 25.0%
Keyword Research 3.5h 15h 23.3%
Project management 0.2h
(No task) 0h
TicketWorkedBudgeted%
🚨 [Future] Buyer Journey / CTA Mapping 19h 10h 190.0%
🚨 Context & Framing Workshop 14.2h 10h 142.5%
🚨 Existing Research Review 10.5h 10h 105.0%
🔥 Art Direction 17.5h 20h 87.5%
Keyword Research 10.2h 15h 68.3%
Discovery Phase Gate: May 12, 2026 1d to gate
Visual Design 50h allocation
~27.6h10.8h31.2h33.8h28.8h9.2hAprMay11 MayJunJulAugSep
~25.8h/wk · on pace with ~27.6h baseline
Ideal (28–40h)Under (<28h)Over (>40h)Logged (past)
Sprint 0Sprint 1Sprint 2Sprint 3
6 Apr13 Apr20 Apr27 Apr4 May11 May18 May25 May
Shannon
Planning
2.2h
9.2h
15.5h
3h
49h6.2h in
16h
27h
Marci
Planning
5h
11.5h
2.5h
17.5h
30h3h in
16h
35h
Todd
Planning
8h
9.5h
1.2h
1.2h
Reid
Planning
1h
1h
30h
Ryan
Planning
1h
Dan
Planning
1h
1.2h
2.5h
Tito
Planning
2.5h
2.5h
3.2h
3.5h
3.5h
3.5h
3.5h
This Week — worked on
“Push CTA mapping to Preliminary IA. No need for workshop, include in Sprint 3 demo.”
(No task)0h
Next Two Weeks — planned
Risk Tracker
Short-term — within 2 weeks
🔥 Overdue — Competitor Website AnalysisData
6 days past due, still open.
🔥 Overdue — Keyword ResearchData
6 days past due, still open.
🔥 Overdue — Directional Messaging Framework & Topic StrategyData
6 days past due, still open.
🔥 Overdue — [Future] Buyer Journey / CTA MappingData
2 days past due, still open.
Content dependency on EAManual
All new copy and CMS content entry is EA's responsibility. Delays in content delivery will directly impact timeline and could push launch.
CMS decision pendingManual
Final platform (WordPress vs. Webflow vs. Framer) is determined in Phase 1. A late or changed decision could compress the dev timeline.
Stakeholder availabilityManual
Key interviews with Dustin Boss and Alicia Torres need to happen early in discovery. Scheduling delays slow the entire strategy phase.
48-hour feedback SLAManual
SOW requires EA to provide feedback within 48 hours. Missed windows compound across phases.
Long-term — 2+ weeks
Buffer budget governanceManual
The $16,500 buffer is only invoiced on the final invoice. Need clear internal tracking so there are no surprises if scope creep triggers it.
AI workflow frictionManual
The AI-forward approach is intended to save time. If tools fail to produce usable drafts, effort may increase beyond estimates.